How to Handle Change Orders in Fixed Price Projects in Dynamics AX 2012

By Dan Liebl | February 14, 2017

There are probably multiple ways to handle change orders in a fixed price project, but here is one way I recently rolled out at a client. They had projects that were not large, but sizeable, and would have situations where there could be multiple change orders during the project. How could they keep track of the hour, and even the item budgets on the projects? It is important to measure how the company is doing versus the budget. If you lose track of the budget, tracking and comparing get difficult. So, I came up with the following process which I will highlight briefly.

The best way I found to track these is with forecast models, such as the example I created below.

Forecast Model Example:

  1. Current, which is the current budget.
  2. Original, which is the original budget being worked against.
  3. Original1, which represents the first change order budget.
  4. Original2, which represents the second change order budget (I would create as many Originals as I thought I would have for any additional change orders, but they can also be created as needed).
  5. Reduction, which is the model against which hours, items and expenses are applied to show remaining.

After doing a run through of an original and three change orders, plus some hours transactions, here is what the hours forecast window looked like:

Change Orders - Forecast model

With the original, I had Engineering, Mechanical and Electrical Assembly (each with 100 hours). On the first change order, I added 50 hours of labor (20 each to Engineering and Mechanical Assembly, and 10 to Electrical Assembly). On the second change order, I reduced it back to the original 100 across the board. On the third change order, I added a new category of Fabrication with an additional 50 hours. After each change order, I would copy to the corresponding forecast model to and overwrite the Current one. I did this because when running reports on a specific forecast model, you need to have consistency over all projects to get the current forecast. It is a bit of duplication, but some projects may not have any change orders and if you want to run a report across multiple projects, you will know that Current will be your current budget.

Note: On the reduction model one thing to note, you do need to manually edit the hours column to account for the change order changes to hours. In that case, I strongly urge taking a screen shot of the window prior to edits as a backup to revert to in the event something goes awry.

I have written about only the hours forecasts here, but this would apply to item or expenses changes as well.


Under the terms of this license, you are authorized to share and redistribute the content across various mediums, subject to adherence to the specified conditions: you must provide proper attribution to Stoneridge as the original creator in a manner that does not imply their endorsement of your use, the material is to be utilized solely for non-commercial purposes, and alterations, modifications, or derivative works based on the original material are strictly prohibited.

Responsibility rests with the licensee to ensure that their use of the material does not violate any other rights.

Start the Conversation

It’s our mission to help clients win. We’d love to talk to you about the right business solutions to help you achieve your goals.

Subscribe To Our Blog

Sign up to get periodic updates on the latest posts.

Thank you for subscribing!