Dynamics AX 2012 Scheduling Options & Sorting Orders

by | Updated December 29, 2017 | Dynamics AX

In Operation and Job Scheduling in Dynamics AX 2012, there are four options for sorting the order in which AX schedules production orders.

4 Options for Sorting Orders in Dynamics AX

  1. Ascending item level, delivery date
  2. Descending item level, delivery date
  3. Priority – delivery date
  4. Status – scheduled start

The first three scheduling options below start with the delivery date of the production order. Orders with the earliest delivery dates are scheduled first. If multiple production orders have the same delivery date AX will sort the production orders as outlined below.

The first three scheduling options start with the delivery date of the production order.

Ascending item level and Descending item level use the BOM level to determine the scheduling order

Ascending item level and Descending item level use the BOM level to determine the scheduling order

Ascending item level, delivery date will schedule items from the lowest BOM level to the highest. Finished goods are scheduled before Semi Finished goods (BOM items that are consumed by other BOMs).

In the example below, a Finished Good and a Semi Finished Good are being scheduled with the same delivery date.

Item: D0001 BOM Level 1 (Finished Good)
Item: D0002 BOM Level 2 (Semi Finished Good)

AX will schedule production order P000209 first because item D0001 has the lowest BOM level.

AX will schedule production order P000209 first because item D0001 has the lowest BOM level.

Few manufacturing scenarios would require Finished Goods to be scheduled before related Semi Finished Goods, so this approach is seldom used.

Descending item level, delivery date will schedule items with the highest BOM level to the lowest. Semi-Finished goods will be scheduled before Finished Goods.

In the example below, a Finished Good and a Semi Finished Good are being job scheduled with the same delivery date. Descending item level, delivery date has been selected.

Item: D0001 BOM Level 1 (Finished Good)
Item: D0002 BOM Level 2 (Semi Finished Good)

AX will schedule production order P000210 first because item D0002 has the highest BOM level

AX will schedule production order P000210 first because item D0002 has the highest BOM level

The opposite of the previous approach, this scheduling order is very commonly used.

To schedule production orders by Priority – delivery date the priority field needs to be manually entered on the production order. The higher the number the higher the priority of the production order.

Schedule production orders by Priority – delivery date: the priority field needs to be manually entered on the production order.

In the example below, I am scheduling two production orders with the same delivery date and the same priority.

AX will schedule production order P000209 first because AX will schedule the lowest production order number first

AX will schedule production order P000209 first because AX will schedule the lowest production order number first

In the next example, I am scheduling two production orders with the same delivery date with priority on production order P0002010 set to 100.

AX scheduled production order P000210 first because it has a higher priority than P000209

AX scheduled production order P000210 first because it has a higher priority than P000209

The last scheduling sorting option on AX is Status – scheduled start. If multiple orders have the same start date the production order in the higher production status will be scheduled first. Production order status from lowest to highest, Scheduled, Released and Started.

In the example below, the two production orders have the same start date. The order in the higher production status will be scheduled first. Production order P000210 is in a released status, released status is a higher status then scheduled. P000210 is scheduled to start at 9:00 AM compared to order P000209 which will not start until 10:00 AM.

The two production orders have the same start date. The order in the higher production status will be scheduled first.

Happy scheduling!

Related Posts

  • The Safari browser is now supported natively on Dynamics AX 2012 R2 as well as being supported on Dynamics AX RTM with a hotfix.  Taken from the updated System Requirements…

  • I put together some certification information on the requirements for Microsoft Dynamics AX 2012 and a proposed training roadmap to get to each of the core certifications.  Rather than have this…

  • With the announcement of the release of Microsoft Dynamics AX 2012 R2, Microsoft released an updated system requirements document for AX 2012: http://www.microsoft.com/en-us/download/details.aspx?id=11094.  Windows 2012 Server is now supported, but…

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Upcoming Events

november

05nov11:00 am12:00 pmConfab with Stoneridge - Livestream - Project Oakdale: The NEW Integration of Power Platform into Teams

18nov10:00 am10:30 amThe Modern Manufacturer - Tears and Trauma of MRP

19nov11:00 am12:00 pmConfab with Stoneridge - Livestream - Project Oaktree: NEW Functionality for Dynamics 365 Manufacturing

december

02dec9:00 am12:00 pmOnline Workshop - Dynamics GP Year End Close (Morning Session)

03dec11:00 am12:00 pmConfab with Stoneridge - Livestream: Live Agents, Power Virtual Agents, Omnichannel – Oh My!

03dec1:00 pm4:00 pmOnline Workshop - Dynamics GP Year End Close (Afternoon Session)

09dec10:00 am10:30 amThe Modern Manufacturer - Manufacturing Policy Management

17dec11:00 am12:00 pmConfab with Stoneridge - Livestream - Technology in 2020: A Year in Review

About Stoneridge
Stoneridge Software is a unique Microsoft Gold Partner, with emphasis on partner. With specialties in Microsoft Dynamics 365, Microsoft Dynamics AX, Microsoft Dynamics NAV, Microsoft Dynamics GP and Microsoft Dynamics CRM, we focus on attracting the most knowledgeable experts in the field to our team, and prioritize delivering stellar solutions with maximum impact for your business. At Stoneridge, we are deeply committed to your results. Each engagement is met with a dedicated team, ready to provide thorough, tailored, and expert service. Based in Minnesota, we intentionally “step into your shoes,” wherever you are. We focus on what you care about, and develop trusting, long-term relationships with our clients.

Subscribe To Our Blog

Sign up to get periodic updates on the latest posts.

Thank you for subscribing!

X